Grouting of Post-Tensioning Ducts
Grouting is the injection of cementitious grout into post-tensioning tendon ducts after stressing, providing bond between tendon and concrete, and protecting th...
Cementitious grouting uses fluid cement-based mixtures poured or pumped to fill cracks, voids, or spaces in concrete — including tendon duct grouting, crack injection, under-sealing slabs, and filling honeycomb. Covers grout types (neat cement; sanded; expanding), placement methods (gravity; pressure; vacuum), and inspection for complete fill and bond.
A grout pour is the controlled placement of a fluid cementitious mixture — comprising portland cement, water, and optionally fine aggregate or chemical admixtures — into a defined cavity, crack, void, duct, or space between existing concrete and substrate, with the purpose of filling that space completely, bonding to the surrounding surfaces, and restoring structural continuity, load transfer, or corrosion protection. The term “grout pour” is used across concrete construction, repair, and maintenance to distinguish the act of placing grout from the material itself (grout) and from the broader process (grouting).

Cementitious grouting is governed by multiple international and national standards. The FHWA Post-Tensioning Tendon Installation and Grouting Manual (FHWA-NHI-13-026) provides comprehensive guidance for grouting of post-tensioning tendons in bridges. The FAA Advisory Circular 150/5370-10H (Standard Specifications for Construction of Airports) references grout for airport pavement repairs, base course stabilization, and anchor installations. The ASTM C476 (Standard Specification for Grout for Masonry) defines fine and coarse grout classifications, and ACI 351.1R (Grouting for Equipment Baseplates) covers precision grouting applications.
The fundamental distinction between a grout pour and concrete placement is the material consistency and purpose. Grout is designed to be fluid enough to flow into narrow spaces under its own weight or moderate pressure, while structural concrete is designed to be placed in forms at a stiffer consistency. Grout typically contains only fine aggregate (sand passing a No. 4 sieve, maximum 4.75 mm) or no aggregate at all, while concrete contains coarse aggregate up to 20 mm or larger. Grout is used for specialized filling, bonding, and repair functions; concrete is used for primary structural elements.
The grout pour must be executed as a continuous operation until the void is completely filled. Interruptions can leave cold joints, voids, or incomplete fill. For large volume grout pours — such as under-slab grouting for pavement undersealing or large honeycomb repairs — multiple injection points are used to ensure complete coverage. For precision applications such as tendon duct grouting, the pour is monitored by observing grout return at outlet ports.
Cementitious grouts are classified by composition into three principal types: neat cement grout, sanded cement grout, and expanding cement grout. Each type has distinct rheological properties, strength characteristics, and application domains.
Neat cement grout consists of portland cement and water only, with no fine aggregate. The water-cement ratio (w/c) typically ranges from 0.35 to 0.50 by weight, though ratios as low as 0.30 may be used for specialized applications requiring maximum strength and minimum shrinkage. The w/c ratio is the single most important determinant of neat cement grout properties.
| Property | Typical Range | Test Method |
|---|---|---|
| Water-cement ratio | 0.35–0.50 | Calculated from batch weights |
| Compressive strength (28-day) | 30–55 MPa | ASTM C109 (50 mm cubes) |
| Flow cone efflux time | 20–60 seconds | ASTM C939 (flow cone method) |
| Bleeding (24 hours) | 0.5–4.0% by volume | ASTM C940 |
| Initial setting time | 2–6 hours | ASTM C191 (Vicat needle) |
| Final setting time | 4–10 hours | ASTM C191 (Vicat needle) |
| Shrinkage (28-day drying) | 2000–4000 microstrain | ASTM C157 |
| Maximum crack penetration | 0.5–1.0 mm | — |
The compressive strength of neat cement grout decreases rapidly with increasing w/c ratio. At w/c = 0.35, 28-day strengths of 50 to 55 MPa are achievable. At w/c = 0.50, strength drops to approximately 25 to 35 MPa. The relationship follows the same water-cement ratio law that governs concrete strength (Abram’s Law), though with a steeper slope because there is no aggregate to contribute mechanical strength.
Neat cement grout is used for crack injection (non-structural) in concrete elements where the crack width is 0.5 to 5.0 mm and where full structural continuity is not required. The FHWA notes that “neat cement grout has been used extensively for filling cracks, ducts around post-tensioning tendons, and small voids” because its fluidity allows penetration into narrow openings. For post-tensioning tendon duct grouting, neat cement grout or a fine sanded grout (with sand passing a No. 16 sieve) is used to ensure complete filling of the interstitial spaces between individual strands within the duct.
A critical limitation of neat cement grout is bleeding — the separation of excess mixing water that rises to the surface after placement while the cement particles settle. Bleeding creates water voids at the top of horizontal or inclined cavities, compromising fill completeness and bond. The ASTM C940 test measures bleeding over a 3-hour period. Acceptable bleeding for post-tensioning grout is less than 2 percent by volume after 3 hours, with reabsorption of bleed water within 24 hours.
Sanded cement grout incorporates fine aggregate (sand) in addition to cement and water, producing a material with improved dimensional stability, reduced shrinkage, higher yield, and better mechanical properties in thicker sections. The sand must pass a No. 16 sieve (1.18 mm) for most grouting applications, and may be up to No. 4 sieve (4.75 mm) for coarse grout applications such as masonry grouting (ASTM C476).
The sand-to-cement ratio by weight ranges from 0.5:1 to 3:1, with 2:1 being the most common for general-purpose grouting. The water-cement ratio is typically 0.45 to 0.55, though additional water may be required to achieve the desired fluidity with higher sand contents. The flow cone efflux time for sanded grout is typically 30 to 60 seconds (ASTM C939), somewhat higher than neat cement grout due to the sand content.

The advantages of sanded grout over neat cement grout include:
Sanded grout is used for:
The maximum aggregate size in sanded grout must be no larger than one-third the minimum opening dimension to prevent particle bridging. For a 10 mm crack, sand passing a No. 16 sieve (1.18 mm) is acceptable. For honeycomb repair where the void opening is 25 mm or larger, sand passing a No. 8 sieve (2.36 mm) or No. 4 sieve (4.75 mm) may be used.
Expanding cementitious grout contains admixtures that produce a controlled expansion in the plastic state, typically 0.5 to 4.0 percent linear expansion, to compensate for settlement and drying shrinkage. The expansion ensures that the grout maintains intimate contact with the surrounding surfaces after setting, providing complete fill and bond.
The most common expanding agent is aluminum powder, added at approximately 0.005 to 0.05 percent by weight of cement. The aluminum powder reacts with the alkaline hydroxide ions (OH⁻) in the cement pore water to produce microscopic hydrogen gas bubbles:
The FHWA Post-Tensioning Tendon Installation and Grouting Manual (FHWA-NHI-13-026) specifies that grout for post-tensioning tendons must have an expansion of 0 to 10 percent while in the plastic state to compensate for bleed water settlement and plastic shrinkage. The expansion must occur before the grout sets (typically within 30 to 60 minutes of mixing) and must not continue after setting, as post-set expansion can damage the surrounding concrete or duct.
Other expanding mechanisms include:
The critical performance requirements for expanding grout are:
The method of placing a grout pour is determined by the geometry of the void, accessibility, required fill completeness, and the properties of the grout itself. Three principal placement methods are used: gravity pour, pressure injection, and vacuum-assisted grouting.
Gravity pour is the simplest placement method, relying on the hydrostatic head of the grout column to fill the cavity from the bottom up or from the highest accessible point downward. The grout is poured from above through a funnel, tremie tube, or funnel-shaped port at the top of the cavity.
The flow characteristics of gravity pouring are governed by the grout’s fluidity (measured by flow cone efflux time per ASTM C939) and the cavity geometry. For a vertical duct of height H (m), diameter d (m), filled with grout of density ρ (kg/m³) and plastic viscosity η (Pa·s), the flow velocity v (m/s) under gravity is approximately:
v ≈ (ρ·g·r²)/(8·η)
where r = d/2 and g = 9.81 m/s². For a typical neat cement grout with η = 0.1 Pa·s and a 50 mm diameter duct, the gravity flow velocity is approximately 0.15 m/s, yielding a volumetric flow rate of approximately 0.3 L/s.
Gravity pouring is suitable only for:
The limitations of gravity pouring include no mechanism for forcing grout into narrow crevices, inability to displace standing water from the void, risk of air entrapment at the top of horizontal or near-horizontal cavities, and slow placement rate compared to pressure methods.
Pressure injection uses a pump to force grout into the cavity at controlled positive pressure, overcoming flow resistance, displacing air and water, and forcing grout into every crevice. This is the most common method for structural grouting applications.
The pumping equipment used for pressure injection includes:
The injection pressure is a critical parameter that must be controlled within specified limits:
| Application | Typical Injection Pressure | Maximum Pressure | Standard/Reference |
|---|---|---|---|
| Post-tensioning duct grouting | 0.3–1.0 MPa (45–145 psi) | 1.0 MPa at pump; 0.5 MPa at anchorage | FHWA-NHI-13-026 |
| Crack injection (cementitious) | 0.3–1.0 MPa (50–150 psi) | 2.0 MPa (290 psi) | ACI 224.1R |
| Slab stabilization (undersealing) | 0.14–0.35 MPa (20–50 psi) | 0.5 MPa (70 psi) | FHWA HIF-20-058 |
| Anchor grouting | 0.5–2.0 MPa (70–290 psi) | 3.5 MPa (500 psi) | — |
| Honeycomb repair | 0.1–0.5 MPa (15–70 psi) | 1.0 MPa (145 psi) | — |
The injection procedure for pressure grouting follows a standardized sequence: surface preparation of the cavity opening, flushing with water, grout mixing in a high-shear colloidal mixer for 3 to 10 minutes, injection at the lowest point of the cavity progressing upward, a pressure hold of 30 seconds to 2 minutes, and port sealing.
The FHWA Post-Tensioning Tendon Installation and Grouting Manual specifies that during grout injection of tendon ducts, “the injection should start at the lowest grout inlet and proceed until grout of the same consistency emerges from the outlet” and that “the grout injection pressure should be limited to 1.0 MPa (145 psi) at the grout pump and 0.5 MPa (70 psi) at the tendon anchorage.”
Vacuum-assisted grouting is a specialized placement method where a vacuum pump creates negative pressure at the outlet port before grout injection begins. The vacuum removes air from the cavity, creating a partial vacuum that draws the grout in and eliminates air pockets. This method achieves the highest level of fill completeness.

The vacuum grouting procedure involves sealing all grout inlet and outlet ports, applying vacuum (3 to 5 kPa absolute, approximately 95 to 97 percent vacuum) for 10 to 30 minutes, injecting grout at the inlet port while maintaining the vacuum, releasing vacuum after grout emerges at the outlet, and sealing all ports.
Vacuum grouting is specified for certain post-tensioning tendon grouting applications — particularly for tendons with complex profiles that include multiple high points (crests) where air would otherwise become trapped. The FHWA manual notes that “vacuum grouting is an effective method for grouting tendons that are not horizontal or have changes in profile that could trap air.”
Slab stabilization (also called undersealing, subsealing, or pavement grouting) is the injection of grout beneath concrete slabs to fill voids created by pumping, subgrade erosion, or consolidation. The purpose is to restore uniform support to the slab, reduce deflections under traffic loading, and extend the pavement service life. The FP2 (Foundation Performance Association) defines slab stabilization as “a nondestructive, void-filling, corrective process that restores slab support.”
The cementitious grout for slab stabilization is typically a sanded grout with sand-cement ratio of 2:1 to 3:1 by weight, water-cement ratio of 0.45 to 0.60, 28-day compressive strength of 7 to 20 MPa, maximum aggregate size of 3 to 6 mm, and slump of 200 to 250 mm.
The grout pour procedure for slab stabilization follows these steps:
The estimated life extension from slab stabilization is 5 to 10 years. The procedure is most effective when performed before the onset of pavement damage (cracking, faulting) caused by loss of support.
Honeycomb in concrete refers to areas where the coarse aggregate is visible on the surface with voids between aggregate particles, caused by inadequate consolidation (vibration) during concrete placement, congested reinforcement that impedes concrete flow, or a concrete mix with insufficient fines content.
The grout pour for honeycomb repair follows a systematic procedure: assessment of extent and depth, cavity preparation (removing loose material and cleaning), formwork placement for larger cavities, grout selection (sanded grout with sand-cement ratio of 1:1 to 2:1 for surface honeycomb, or coarser grout for deeper voids), grout placement by pouring or injection from the bottom up, and moist curing for 3 to 7 days.
The quality of the grout repair is assessed by visual inspection, sounding (tapping produces a solid sound), pull-off testing (ASTM C1583, minimum bond strength of 1.5 MPa for structural repairs), and core extraction to verify complete fill.
The grouting of post-tensioning tendon ducts is a specialized application with the most stringent requirements of any cementitious grouting operation. The grout serves two critical functions: corrosion protection of the prestressing steel and bonding between the tendon and the surrounding concrete. The FHWA Post-Tensioning Tendon Installation and Grouting Manual (FHWA-NHI-13-026) is the definitive reference.
Grout materials for post-tensioning ducts must meet specific performance requirements: 28-day compressive strength minimum 30 MPa, maximum water-cement ratio of 0.45, bleeding less than 2 percent after 3 hours, expansion of 0 to 10 percent in the plastic state, flow cone efflux time of 20 to 45 seconds, chloride ion content less than 0.1 percent by mass of cementitious materials, and sulfate content less than 4 percent.
The grout pour procedure for post-tensioning ducts includes pre-grouting inspection of the duct system, grout mixing in a high-shear colloidal mixer, on-site testing (flow cone every 5 batches, temperature every batch, bleeding test at start of production, compressive strength three cubes per day), grout injection at the lowest inlet port at 0.3 to 1.0 MPa, grout venting until same consistency grout emerges, and post-grouting sealing of all ports.
The FHWA Guidelines for Sampling, Assessing, and Restoring Defective Grout (FHWA-HRT-13-028) define physical deficiencies (PDs) of grout as “air voids, free water, and unhardened, segregated, or separated grout” and chemical deficiencies (CDs) as “chloride concentration in excess of what is specified.”
Inspection of a completed grout pour is essential to verify that the void has been completely filled and that the grout has achieved the required properties.
| Inspection Method | Application | Standard | Detection Capability |
|---|---|---|---|
| Visual observation of grout return | Pressure grouting | — | Confirms grout emergence at outlet |
| Core sampling | All grout types | ASTM C42 | Direct visual examination of fill and bond |
| Borescope inspection | Ducts, drilled holes | — | Visual inspection through small-diameter hole |
| Impact-echo testing | Ducts, slab-subgrade interface | ASTM C1383 | Detects voids larger than 25 mm diameter |
| Ultrasonic pulse velocity | Ducts, tendon ducts | ASTM C597 | Measures signal transit time; voids increase time |
| Ground penetrating radar | Slab-subgrade voids, ducts | — | Detects dielectric contrast at interfaces |
| Infrared thermography | Slab-subgrade voids | — | Detects thermal anomalies from voids |
| Grout volume accounting | All grout types | — | Compares injected volume to theoretical volume |
| Pull-off bond testing | Surface repairs | ASTM C1583 | Measures tensile bond strength |
| Flow cone (fresh grout) | Quality control | ASTM C939 | Verifies grout fluidity |
Core sampling is the most definitive method for verifying grout fill completeness. A 50 to 100 mm diameter core is extracted through the grouted area, extending 25 to 50 mm into the surrounding concrete on both sides. The core is examined for grout continuity, bond interface condition, grout hardness and uniformity, and color consistency.
The acceptance criteria for grout fill completeness vary by application:
Airport concrete pavements present unique requirements for cementitious grouting because of the combination of high wheel loads (aircraft weighing up to 600 metric tons for an A380), high tire pressures (up to 1.5 MPa), and the operational need for smooth, defect-free surfaces. The FAA Advisory Circular 150/5370-10H (Standard Specifications for Construction of Airports) and ICAO Aerodrome Design Manual (Doc 9157, Part 3) provide specifications for grouting in airport pavement applications.
Airport-specific grouting applications include:
The ICAO Airport Services Manual (Doc 9137, Part 2 — Pavement Surface Conditions) notes that pumping should be recorded during airport pavement condition surveys, and that slabs showing evidence of pumping should be investigated for subsurface voids. The recommended method for void detection in airport pavements is FWD testing, following FAA AC 150/5320-6G Appendix C.
Quality assurance for grout pours in airport pavements follows FAA requirements: grout materials must be certified, mixing must be documented, compressive strength tests must be performed at one set of three 50 mm cubes per day of grouting, post-grouting FWD testing must verify void filling effectiveness, and core samples must be extracted at a rate of one core per 100 m² of grouted area.
| Parameter | Neat Cement Grout | Sanded Cement Grout | Expanding Cement Grout |
|---|---|---|---|
| Composition | Cement + water | Cement + sand + water | Cement + sand + water + expanding agent |
| Water-cement ratio | 0.35–0.50 | 0.45–0.55 | 0.40–0.50 |
| Sand-cement ratio | — | 0.5:1 to 3:1 | 1:1 to 2:1 |
| 28-day compressive strength | 30–55 MPa | 20–40 MPa | 30–50 MPa |
| Expansion | None | None | 0.5–4.0% (plastic state) |
| Bleeding (24 hr) | 0.5–4.0% | 0.5–2.0% | < 0.5% |
| Flow cone time (ASTM C939) | 20–60 sec | 30–60 sec | 25–50 sec |
| Minimum crack filling width | 0.5–1.0 mm | 3.0–5.0 mm | 0.5–2.0 mm |
| Maximum pour thickness (single lift) | 25–50 mm | 50–150 mm | 50–200 mm |
| Typical applications | Crack injection, duct grouting, anchorage | Slabjacking, honeycomb repair, baseplate grouting | Tendon duct grouting, anchor grouting |
The selection of the appropriate grout type and placement method for a grout pour depends on the void geometry, accessibility, performance requirements, and cost. Neat cement grout offers the highest fluidity and penetration capability but the highest shrinkage and bleeding risk. Sanded grout offers better dimensional stability and lower cost but cannot penetrate narrow openings. Expanding grout combines the advantages of both with the added benefit of shrinkage compensation, but at higher material cost and with more demanding quality control requirements.
Proper execution of a grout pour — including surface preparation, mixing, placement, curing, and inspection — is as important to the success of the repair as the material selection. The FHWA, FAA, ACI, and ASTM standards provide comprehensive guidance for each of these elements, and compliance with the applicable standards is essential for achieving a durable, effective grout repair.
TarmacView provides AI-powered pavement inspection solutions that help identify areas requiring grout repair and verify the quality of completed grouting work. Schedule a demonstration to see how our technology enhances quality assurance for cementitious grouting operations.
Grouting is the injection of cementitious grout into post-tensioning tendon ducts after stressing, providing bond between tendon and concrete, and protecting th...
Dry pack mortar is a very stiff, low-water-content cement mortar rammed into confined repair areas (spall pockets, cone bolt holes, narrow slots), achieving hig...
Pervious concrete (also called permeable or porous concrete) is a concrete with high interconnected void content (15-35%) allowing water to pass through, reduci...