What is a profile in surveying?
Definition
A profile, also called a longitudinal profile, is a graph of ground elevation along a survey line. The horizontal axis is the distance along the line. The vertical axis is elevation.
A cross-section is the ground shape across the survey line, at one station.
The line is often the centerline of a road, canal or runway. FAO calls the graph a ground profile. Surveyors do profile leveling to get the elevations for it. On a construction drawing, the profile of the existing ground sits next to the finished profile grade. FDOT uses the finished profile grades to build the finished template at each cross-section. The difference between the two is the cut or fill.
Longitudinal profile and cross-section
FAO describes the two kinds of profile in its topography manual. A longitudinal profile follows the main axis of the survey, such as the centerline of a canal. A cross-section runs perpendicular to that axis. The surveyor uses the points of known elevation on the longitudinal profile as benchmarks for the cross-sections.
FAO puts cross-sections at the points where the profile needs more information. At a turn in the line, it makes two cross-sections, one for each straight section. The points on a cross-section do not need regular spacing. They sit where the terrain changes, because these are the changes of slope.
A cross-section shows the ground on both sides of the line.
Chainage and stations
Chainage, also called stationing, is the distance along the alignment from a zero point. The zero point is arbitrary. Each cross-section sits at a station, which is a chainage value. A chainage-offset system gives each point two numbers. These are the chainage along the centerline and the offset from it. A surveyor collects ground elevation and feature data along each cross-section, relative to the centerline.
In US customary units, a station is 100 ft. Caltrans bases plan sheet stationing on 100 feet per station. A point 1,250 ft along the line is station 12+50. In metric projects the plus sign often separates the third and fourth places, so 1+250 means 1,250 m from the zero point.
Measuring the elevations
Surveyors use differential leveling to measure elevations:
- A rod stands on a point of known elevation. The level reading on this rod is the backsight (BS).
- The backsight plus the known elevation gives the elevation of the line of sight. This is the height of instrument (HI).
- A rod stands on a new point. The reading on this rod is the foresight (FS).
- The height of instrument minus the foresight gives the elevation of the new point.
- The surveyor moves the level forward. The points that hold the rod between setups are turning points.
A foresight to a point off the main line is a sideshot.
The FAO example for a canal centerline marks a stake every 25 m. It adds points between the stakes where the slope changes clearly. Each stake carries its cumulative distance from the start. The elevations and the distances give the points of the profile.
Caltrans sets rules for the fixed points. A turning point goes in a stable, protected location. A well-defined turning point can serve as a temporary benchmark.
Other ways to get a profile
Leveling is not the only source. FDOT says the cross-sections of the existing surface usually come from field survey or photogrammetry.
A digital terrain model (DTM) is a model of the ground surface built from survey points. Caltrans builds one from points on breaklines. A breakline is a line where the slope changes, such as the edge of pavement or the toe of a slope. The points are close enough to define the profile of each breakline. Cross-sections can then be generated from the finished DTM for any alignment. New sets of cross-sections are easy to produce after an alignment change. Caltrans notes that photogrammetry is in most cases more cost effective than field methods for a DTM.
The Caltrans Surveys Manual also states an accuracy standard for the elevations of profiles and cross-sections that are measured photogrammetrically. The standard applies at every centerline station and at points of change in ground slope.
Plotting a profile
A plotted profile uses two scales. The horizontal scale reduces ground distances. The vertical scale reduces elevations. Both use the same unit of length.
FAO notes that in most aquaculture surveys the elevation differences are very small next to the horizontal distances. The plot then needs a larger vertical scale. Caltrans gives these common scales for roadway profile sheets, and each has a vertical scale 10 times the horizontal scale:
- Rural hilly or mountainous terrain: 1 in = 10 ft vertical and 1 in = 100 ft horizontal.
- Rural or urban gentle rolling terrain: 1 in = 5 ft vertical and 1 in = 50 ft horizontal.
- Rural or urban level terrain: 1 in = 2 ft vertical and 1 in = 20 ft horizontal.
FAO gives a vertical scale 10 to 100 times larger than the horizontal scale for aquaculture surveys. A cross-section for an earthwork estimate is different. FAO uses identical horizontal and vertical scales so that the scaled area is true. Caltrans plots earthwork cross-sections at 1 in = 10 ft for rural projects and 1 in = 5 ft for urban projects. This applies to both scales. Its interval is not more than 50 ft.
Earthwork volumes
A designer uses the existing cross-sections and the finished profile grades to compute cut and fill. The Florida DOT Design Manual calculates earthwork with the average end area method:
cubic yards = (EA1 + EA2) / 2 x length / 27
EA1 and EA2 are the areas of two successive cross-sections in square feet. The length is the distance between them in feet. The factor 27 converts cubic feet to cubic yards. The manual says that the interval between cross-sections varies with the project. It names the choice of an inappropriate interval as a primary cause of inaccurate quantities. It asks for an interval of 25 ft or less on ramps and sharp turning roadways.
Profile and runway design
CS-ADR-DSN gives limits for the profile of the runway centerline. ICAO Annex 14 gives the same values as Recommendations.
- Overall slope. In CS ADR-DSN.B.060, the slope is the difference between the maximum and minimum elevation along the centerline, divided by the runway length. This slope should not exceed 1 % where the code number is 3 or 4. It should not exceed 2 % where the code number is 1 or 2.
- Slope on any part. No portion of a runway should exceed a set slope. The limit is 1.25 % for code number 4, 1.5 % for code number 3, and 2 % for code number 1 or 2. For code number 4, the first and last quarter of the runway should not exceed 0.8 %. The same 0.8 % applies to the first and last quarter of a code number 3 precision approach runway of Category II or III.
- Slope changes. A slope change that cannot be avoided has a limit (B.065). It is 1.5 % for code number 3 or 4, and 2 % for code number 1 or 2. The transition is a curved surface. Its rate of change is at most 0.1 % per 30 m for code number 4. It is 0.2 % per 30 m for code number 3, and 0.4 % per 30 m for code number 1 or 2.
- Sight distance. Where slope changes exist, there should be a clear line of sight between points above the runway (B.070). The line covers at least half the runway length. The height is 3 m for code letters C to F, 2 m for code letter B and 1.5 m for code letter A.
- Distance between slope changes. CS ADR-DSN.B.075 sets the distance between two successive slope changes. Add the absolute values of the two slope changes. Multiply the sum by 30,000 m for code number 4, 15,000 m for code number 3, or 5,000 m for code numbers 1 and 2. The distance should not be less than this result or 45 m, whichever is greater.
The EASA guidance gives a worked example for code number 3. The slopes are +1.0 %, -0.5 % and +0.5 %. The slope changes are 1.5 % and 1.0 %. The distance is at least 15,000 m x 0.025, which is 375 m.
The transverse slope is a cross-section value. For a cambered runway, CS ADR-DSN.B.080 gives 1 % to 1.5 % for code letters C, D, E and F. It gives 1 % to 2 % for code letters A and B. The slope on each side of the centerline is symmetrical.
FAA sets its own limits in AC 150/5300-13B, section 3.16. For approach categories A and B, the maximum longitudinal grade is 2.0 %. For categories C, D and E, it is 1.5 %. For categories C, D and E, a grade above 0.8 % is not acceptable within the lesser of two lengths. These are the first and last quarter of the runway, and the first and last 2,500 ft. See longitudinal grade .
Profile and cross-sections in airfield construction
The FAA guide specification for asphalt pavement, Item P-401, uses cross-sections to accept the finished surface. A licensed surveyor surveys the finished surface. The cross-sections are taken at a set longitudinal spacing, at all grade breaks, and at the start and end of each lane. The grade elevations must not deviate more than 1/2 inch (12 mm) vertically from the plans.
P-401 also has an option for a profilograph roughness test on runway and taxiway projects longer than 500 ft (150 m). The test uses an ASTM E1274 profilograph or an ASTM E950 Class I inertial profiler. Item P-152 sets limits for the subgrade under a subbase or base course. The surface may vary by 1/2 inch (12 mm) under a 12 ft (3.7 m) straightedge. The specification checks the grade on a 50 ft (15 m) grid, within 0.05 ft (15 mm).
Other meanings of profile
In runway surface work, “profile” can also mean a measured line of surface height. The mean profile depth (MPD) is a measure of surface texture that comes from such a profile. CS-ADR-DSN refers to ISO 13473-1 for it. EASA notes that MPD comes from a two-dimensional profile, not a three-dimensional surface. This is not a survey profile.
Frequently Asked Questions
- What is a longitudinal profile?
- A longitudinal profile is a graph of ground elevation along a survey line. The horizontal axis is the distance along the line. The vertical axis is elevation. The line is often the centerline of a road, canal or runway.
- What is the difference between a profile and a cross-section?
- A profile follows the survey line, and a cross-section cuts across it. A longitudinal profile shows elevation along the line. A cross-section shows the ground across the line, at one station.
- What is chainage?
- Chainage, or stationing, is the distance along the alignment from a zero point. The zero point is arbitrary. In metric projects the number often has a plus sign, so 1+250 means 1,250 m from the zero point.
- How do surveyors get elevations for a profile?
- They use differential leveling. A rod reading on a point of known elevation is the backsight. Adding it to that elevation gives the height of instrument. A reading on a new point is the foresight, and subtracting it from the height of instrument gives the elevation of the new point.
- Why is the vertical scale of a profile larger than the horizontal scale?
- The enlarged vertical scale makes small elevation changes visible. Caltrans uses 1 inch = 10 ft vertical and 1 inch = 100 ft horizontal for roadway profile sheets in hilly rural terrain. FAO gives a vertical scale 10 to 100 times larger for aquaculture surveys.
- How do you calculate earthwork volume from cross-sections?
- The average end area method averages the areas of two successive cross-sections and multiplies by the distance between them. The Florida DOT Design Manual gives it as cubic yards = (EA1 + EA2) / 2 x length / 27. The end areas are in square feet and the length is in feet.
- What slope limits apply to the profile of a runway?
- The overall slope is the difference between the highest and lowest centerline points, divided by the runway length. For code number 3 or 4 it should not exceed 1 %. For code number 1 or 2, the limit is 2 %. CS ADR-DSN.B.060 also limits the slope along any part of the runway.
- Can surveyors get a profile from aerial photographs?
- Yes. The Florida DOT Design Manual says field survey or photogrammetry usually gives the cross-sections of the existing surface. The Caltrans Surveys Manual also states an elevation accuracy standard for profiles and cross-sections that are measured photogrammetrically.
References
- usace-em-1110-1-1005
- Control and Topographic Surveying, Part 2 (course based on USACE EM 1110-1-1005) CEDengineering
- fao-topography-ch8
- Topography (FAO Training Series), Chapter 8: Topographical Surveys, Direct Levelling FAO
- fao-topography-ch9
- Topography (FAO Training Series), Chapter 9: Topographical Plans and Maps FAO
- caltrans-ppm-ch2
- Plans Preparation Manual (U.S. Customary Units), Chapter 2 Project Plans, September 2018 Caltrans
- caltrans-surveys-ch8
- Surveys Manual, Chapter 8 Differential Leveling Survey Specifications (September 2006) Caltrans
- caltrans-surveys-ch11
- Surveys Manual, Chapter 11 Engineering Surveys (September 2006) Caltrans
- caltrans-surveys-ch13
- Surveys Manual, Chapter 13 Photogrammetry Surveys (September 2006), Appendix 13C Caltrans
- fdot-fdm-216
- FDOT Design Manual, 216 Earthwork Florida Department of Transportation
- easa-cs-adr-dsn
- Easy Access Rules for Aerodromes (Regulation (EU) No 139/2014), CS-ADR-DSN Issue 7, Chapter B EASA
- icao-annex-14-vol-i
- Annex 14 to the Convention on International Civil Aviation, Aerodromes, Volume I, Aerodrome Design and Operations, 9th edition (July 2022) ICAO
- faa-ac-150-5300-13b
- AC 150/5300-13B, Airport Design FAA
- faa-ac-150-5370-10h
- AC 150/5370-10H, Standard Specifications for Construction of Airports FAA