What is a Contingency?

Aerodrome Operations · Safety 8 languages
Definition
A contingency is a prepared measure that an operator uses when a normal system, procedure or resource fails or is not available.

A contingency is a prepared measure that an operator uses when a normal system, procedure or resource fails or is not available.

What it means

A contingency is a possible event that you plan for. A contingency plan lists what to do if that event happens. It names a trigger, the people who act, the steps and the way back to normal. NIST describes contingency planning as interim measures to recover services after a disruption. The measures may move work to an alternate site, use alternate equipment or use manual methods (NIST SP 800-34 Rev. 1).

Contingency, emergency and other plans

Organisations use several plans, and each has a different job. NIST lists them as separate plans (section 2.2).

  • Contingency plan. Restores a system or process after a failure. NIST calls the version for an information system the ISCP.
  • Business continuity plan. Keeps the mission and business processes running during and after a disruption.
  • Disaster recovery plan. Moves an information system to an alternate site after a major physical disruption.
  • Cyber incident response plan. Handles attacks on information systems.
  • Crisis communications plan. Sets who speaks to staff and the public.
  • Occupant emergency plan. Gives first-response steps for people in a building, for example in a fire.

In the aerodrome rules, an emergency plan is not the same as the aerodrome contingency measures. The emergency plan coordinates the response to an event. A contingency measure covers the loss of a service.

How to build a contingency plan

NIST gives a seven-step process (Executive Summary):

  1. Write a policy that gives the authority to plan.
  2. Run a business impact analysis (BIA).
  3. Identify preventive controls.
  4. Create recovery strategies.
  5. Write the plan.
  6. Test, train and exercise.
  7. Maintain the plan, so that it stays current.

NIST says that testing validates recovery capabilities, training prepares the people, and exercises show gaps in the plan. A sample NIST policy asks for a review and a test at least once a year.

Business impact analysis

The BIA finds the processes that matter and how long each can stop. It gives three values (section 3.2):

  • Maximum tolerable downtime (MTD). The total outage time that the owner will accept for a process.
  • Recovery time objective (RTO). The longest time that a system resource can stay unavailable before the impact is unacceptable.
  • Recovery point objective (RPO). The point in time to which data can be recovered, given the latest backup.

RTO must be shorter than MTD, because reprocessing takes time. Example: the MTD of a process is 8 hours and reprocessing the data takes 2 hours. The RTO must then be 6 hours or less. RPO is a separate limit. It sets how much data loss the process can accept.

Contingency in EASA aerodrome rules

EASA guidance material (GM) uses the word for a planned alternative to a named failure.

  • Stop bars. If a lit stop bar cannot be turned off, EASA lists contingency measures that may be considered. The operator can disconnect the stop bar from its power, obscure its lights, or use a different route. A marshaller or follow-me vehicle may be needed. A lit stop bar must still not be crossed, and the operator needs to take maintenance action as soon as possible (GM1 ADR.OPS.B.065).
  • Rescue and firefighting. The operator should develop contingency arrangements to limit changes to the published level of protection. Examples are a maintenance plan for the vehicles and cover for unplanned absence of the minimum staff (GM4 ADR.OPS.B.010(a)(2)).

These are guidance. They describe measures that an operator may use. They are not rules.

Aerodrome emergency plan

Regulation (EU) No 139/2014 requires an operator to have and implement an aerodrome emergency plan. The plan fits the aircraft operations at the aerodrome and coordinates the organisations that respond to an emergency. It also has procedures to test it and to review the results (ADR.OPS.B.005). EASA guidance says to hold a full-scale exercise at intervals of not more than two years, with partial exercises in between (AMC1 ADR.OPS.B.005(c)).

ICAO Annex 14 requires an aerodrome emergency plan as a Standard (9.1.1 and 9.1.2). Its examples of emergencies include aircraft emergencies, building fires, natural disasters and public health emergencies.

In the United States, 14 CFR 139.325 lists the emergencies that the plan must cover. One of them is power failure that affects movement area lighting. The holder reviews the plan every 12 consecutive calendar months. A Class I holder runs a full-scale exercise every 36 consecutive calendar months.

Contingency for airfield lighting

Lighting has its own built-in contingency. ICAO Annex 14 requires a secondary power supply for a precision approach runway. The connections must switch to it automatically when the primary source fails (8.1.6). Table 8-1 sets the maximum switch-over time. On a category II or III runway it is 1 second for the inner 300 m of the approach lights. It is also 1 second for the threshold, runway end, centre line, touchdown zone and all stop bars. Runway edge lights and most other lights have 15 seconds.

A lighting inspection that finds lamps out or a light out of alignment gives the operator the facts to apply its own measures. TarmacView inspects airfield lighting with a drone. It does not write contingency or emergency plans.

Other use: GPS

In the GPS standard, a contingency upload is an unscheduled update of one satellite’s navigation message. The control segment can do it when the range error of the satellite grows. The standard does not require it (Appendix A.4.4).

Frequently Asked Questions

What is a contingency plan?
A contingency plan is a set of prepared actions for when a normal system, procedure or resource is not available. NIST describes contingency planning as interim measures to recover services after a disruption. EASA gives two aerodrome examples: an unserviceable stop bar and a shortage of firefighting staff.
What is the difference between a contingency plan and an emergency plan?
A contingency plan restores a service or process after a failure. An emergency plan coordinates the response to a threat to people or property. The aerodrome emergency plan covers events such as an aircraft accident or a fire and coordinates all responding agencies. A contingency measure covers the loss of something, such as a stop bar or a rescue vehicle.
What are the steps of contingency planning?
NIST SP 800-34 gives seven steps. Write a policy, run a business impact analysis, identify preventive controls, create recovery strategies, write the plan, test and train, and maintain the plan. The same order works outside information technology.
What is a business impact analysis?
A business impact analysis finds which processes and systems matter most and how long each can be down. It sets the maximum tolerable downtime and the recovery time objective. NIST SP 800-34 describes it as step two of contingency planning.
What do RTO and RPO mean?
The recovery time objective (RTO) is the longest time a system can stay unavailable before the impact becomes unacceptable. The recovery point objective (RPO) is the point in time to which data can be recovered, given the latest backup. RTO must be shorter than the maximum tolerable downtime.
How often must an aerodrome test its emergency plan?
EASA guidance says to hold a full-scale exercise at intervals of not more than two years, with partial exercises in between. The rule itself only requires procedures for periodic testing. In the United States, 14 CFR 139.325 requires a plan review every 12 months and a full-scale exercise every 36 months for Class I airports.
Does a contingency plan apply to airfield lighting?
Yes. ICAO Annex 14 requires a secondary power supply for a precision approach runway, with switch-over times of 1 or 15 seconds. EASA lists measures for a stop bar that cannot be turned off. The US rule names power failure on movement area lighting.

This is a reference entry. TarmacView provides drone inspection services and doesn't sell the equipment or materials described in this glossary.

Get Started Need your airfield lighting verified? TarmacView inspects approach, runway and taxiway lights and the runway surface by drone, during full airport operation. The lighting protocol comes the same day.
Keep reading

Learn more

03 PAGES
Switchover
glossary

Switchover

A switchover is a planned, controlled process that transfers operations from a primary to a backup system, ensuring continuous service in aviation, IT, and other critical sectors. Unlike failover, switchover is deliberate and typically used for maintenance, upgrades, or compliance, with minimal downtime or data loss.

Back-Up System
glossary

Back-Up System

A back-up system, or redundant system, is a safety-critical architecture that ensures continuous operation of vital services during failures, maintenance, or emergencies. It eliminates single points of failure through duplication and layered defenses, foundational to aviation, data centers, healthcare, and more.

Continuous Operations (COOP)
glossary

Continuous Operations (COOP)

Continuous Operations (COOP) ensure essential business processes remain uninterrupted during disruptions like disasters or cyberattacks. COOP is crucial in aviation, finance, and critical infrastructure, relying on automation, redundancy, and disaster recovery to maintain service continuity, safety, and compliance.