What is a Survey Control Point?
Survey Control Point
Definition
A survey control point is a marked point on the ground whose position or elevation surveyors use to find other points. The FAA calls it a control station.
The point carries coordinates in a stated datum. A later survey measures from it and checks against it. The FAA ties all Air Operations Area surveying and positioning to the National Spatial Reference System (NSRS). This is why the control point matters on an airfield. AC 150/5300-17C requires survey control for every remote sensing project, such as aerial imagery, so that the data register to the NSRS.
Types of control point
The Federal Geodetic Control Committee (FGCC) describes three networks in the United States:
- A horizontal network gives geodetic latitude and longitude.
- A vertical network gives elevations.
- A gravity network gives gravity values.
A station can be a control point in one, two or all three networks. The FAA also defines the bench mark. It is a relatively permanent natural or artificial object that bears a marked point of known elevation above or below a datum.
A control point can be permanent or temporary. The FGCC says that a 30-centimeter wooden stake lacks permanence and horizontal stability. A permanent mark can replace a temporary one, but only if survey observations of sufficient accuracy connect the two. A crew sets aerial targets and surveys them before the photography, so these are temporary marks (see below).
The monument
The mark is a monument. The NGS names three needs: it must stay stable, last a long time, and be easy for later surveyors to find. Makers use non-corroding materials such as bronze, brass and concrete. The NGS adds that today a mark also needs a clear view of the sky, so that satellite receivers work well on it.
A 1984 federal standard asks for a corrosion resistant metal disk set in a large concrete mass. It asks first-order and second-order class I points to have more marks. These are an underground mark, two reference marks at right angles and an azimuth mark at least 400 m away.
Each mark has a written description. It says where the mark is, how to reach it, and its distances and directions to nearby objects. Construction equipment, highway maintenance, erosion and vandals destroy many marks each year. A destroyed mark can no longer serve surveyors or engineers.
Accuracy classes
The FGCC classifies horizontal control points by distance accuracy. This is the ratio of the relative position error of a pair of points to their separation. A ratio of 1:100,000 means an error of 1 cm in 1 km. The 1984 standard sets these minimum values:
| Class | Minimum distance accuracy |
|---|---|
| First-order | 1:100,000 |
| Second-order, class I | 1:50,000 |
| Second-order, class II | 1:20,000 |
| Third-order, class I | 1:10,000 |
| Third-order, class II | 1:5,000 |
The class is not the closure of one survey. The FGCC classifies a point by how well the new survey repeats the values of the existing network. NGS can certify a survey only if it connects to the national network. The FGCC standard is from 1984. This page did not check later NGS standards.
Datums
A coordinate has meaning only inside a datum. ICAO Annex 14 and EASA rule ADR.OPS.A.020 require WGS-84 for horizontal positions at aerodromes. EASA guidance names ETRS and national reference systems as other examples of terrestrial reference systems. The rule itself requires WGS-84 for air navigation. The FAA survey standard for US airports uses NAD83 and NAVD 88. The year of the NAD83 adjustment is on the NGS data sheet.
Both ICAO and EASA require mean sea level as the vertical reference. Mean sea level is close to the geoid. Heights above it are orthometric heights. GNSS gives ellipsoid heights. The FAA gives the relation as ellipsoid height = geoid height + orthometric height. The difference between the WGS-84 ellipsoid height and the orthometric height is the geoid undulation.
Vertical control has a use in aerodrome data. Annex 14 asks that the aerodrome elevation and geoid undulation be measured to one-half metre or foot. For a precision approach runway threshold, the accuracy is one-quarter metre or foot. EASA notes that a local geoid model can give centimeter accuracy over several hundred kilometers, where a global model is less accurate.
Airport control stations
In the United States, airport surveys start from the Primary Airport Control Station (PACS) and the Secondary Airport Control Stations (SACS). NGS must declare each station. A PACS ties directly to the NSRS, and a SACS ties to the PACS. The FAA says that PACS meet high-stability and high-accuracy standards. SACS have slightly less strict specifications. NGS lists the airports that have them.
The FAA asks the following:
- Use the PACS and SACS as starting control for all airside surveys.
- When a local control grid is built for engineering, tie it directly to existing stations with published NSRS coordinates.
- Put at least two existing, recoverable stations into the local network.
- Before use, visit each PACS and SACS, check its identity, and check that it has not moved. Record its condition, stability and visibility.
- Measure two independent GPS sessions of at least 10 minutes each, at a 5-second interval, between the PACS and each SACS. A calibrated electronic distance meter can replace them. Compare the result with the published positions. The distances must agree within 3 cm, the ellipsoid height differences within 4 cm and the orthometric height differences within 5 cm. If not, collect the data again.
- Send a recovery report to NGS. If a station is missing or damaged, contact the FAA Airport Surveying-GIS Program Manager.
New stations need long GNSS sessions. On a new PACS, NGS asks for two simultaneous sessions of 4 hours or more. A new SACS needs two sessions of 2 hours or more. NGS checks that two solutions from separate occupations agree within 3 cm horizontally and 5 cm in ellipsoid height.
In construction, the engineer sets horizontal and vertical control through a State licensed land surveyor. The contractor checks all control points before work starts and certifies the result in writing. The contractor also keeps the control intact.
Control for aerial images
A ground control point (GCP) is a control point that an image can show. Crews place targets and measure them before the flight. AC 150/5300-17C describes a good image control point as very small, recognizable and symmetrical, with a distinct boundary between higher and lower contrast. Examples are the junction of two sidewalks, the corner of a parking lot, and a pre-marked or paneled point.
AC 150/5300-17C covers aerial imagery and does not name drones. It sets no minimum number of control points. The number and placement must be enough to georeference the imagery to the accuracy that the project needs. For each control point the surveyor provides a station location and visibility diagram, digital photos with a caption, and a file with the positions. The AC says to determine the positions with NGS OPUS.
A check point is a separate point that the georeferencing does not use. For aerial imagery the AC asks for at least five check points that NGS OPUS positions. To state the accuracy of features taken from images, the FAA asks for the RMSE of twenty or more checkpoints. The surveyor compares the checkpoint coordinates with values from an independent source of higher accuracy. If fewer than twenty checkpoints exist, the report gives a deductive estimate.
Where to find control points
An NGS paper (undated) says that the NGS database holds more than 1,500,000 survey points. The data sheets are free online. The database includes marks from other agencies and private firms. The data sheet shows the coordinates and the year of the adjustment.
Frequently Asked Questions
- What is a survey control point?
- A survey control point is a marked point on the ground whose position or elevation surveyors use to find other points. The FAA calls it a control station. The point carries coordinates in a stated datum, and later surveys start from it.
- What are survey control points used for?
- Surveyors use control points as the starting point and the check for other measurements. On an airport, the FAA asks surveyors to start every airside survey from the airport control stations. For aerial images, control points tie the data to the National Spatial Reference System.
- What is the difference between a survey control point and a ground control point?
- A ground control point (GCP) is a control point that an aerial image can show. An example is a target that the survey crew placed and measured before the flight. A survey control point does not need to be visible from the air.
- What is the difference between horizontal and vertical control?
- A horizontal control point carries a published latitude and longitude. A vertical control point carries a published elevation. One station can be a control point in the horizontal network, the vertical network, or both.
- Which datum do airport coordinates use?
- ICAO Annex 14 and EASA rule ADR.OPS.A.020 require the World Geodetic System 1984 (WGS-84) for horizontal positions. EASA also requires mean sea level as the vertical reference. The FAA survey standard for US airports uses NAD83 and NAVD 88.
- How many ground control points does an aerial survey need?
- FAA AC 150/5300-17C sets no minimum number of control points. The number and placement must be enough to georeference the imagery to the accuracy that the project needs. The AC does ask for at least five separate check points for aerial imagery.
- What are the PACS and SACS?
- The Primary Airport Control Station (PACS) and the Secondary Airport Control Stations (SACS) are control stations on or near a US airport. NGS must declare them. A PACS ties directly to the National Spatial Reference System, and a SACS ties to the PACS. The FAA uses them as the starting control for airside surveys.
References
- faa-ac-150-5300-18b
- AC 150/5300-18B, General Guidance and Specifications for Submission of Aeronautical Surveys to NGS FAA
- faa-ac-150-5300-17c
- AC 150/5300-17C Change 1, Standards for Using Remote Sensing Technologies in Airport Surveys FAA
- ngs-opus-projects-faa
- OPUS Projects User Guide, Appendix E: FAA Airport Surveys NOAA National Geodetic Survey
- ngs-survey-marks
- Bottles, Pots and Pans? Marking the Surveys of the U.S. Coast and Geodetic Survey and NOAA (G. E. Leigh) NOAA National Geodetic Survey
- fgcc-1984
- Standards and Specifications for Geodetic Control Networks Federal Geodetic Control Committee
- faa-ac-150-5370-10h
- AC 150/5370-10H, Standard Specifications for Construction of Airports FAA
- icao-annex-14-vol-i
- Annex 14 Volume I, Aerodrome Design and Operations, 9th edition ICAO
- easa-ear-aerodromes
- Easy Access Rules for Aerodromes (Regulation (EU) No 139/2014) EASA