Definition
A deduct value is the number that an ASTM D5340 deduct curve gives for one distress type at one severity and density.

Deduct Value (PCI)

Definition

A deduct value (DV) is the number that an ASTM D5340 curve gives for one distress at one severity and density.

The Pavement Condition Index (PCI) rates a pavement from 0 to 100. The deduct values are the inputs to that rating. The standard turns them into a corrected deduct value (CDV), and the PCI is 100 minus the maximum CDV. The PCI page covers the whole index, the survey and the rating scale. This page covers the deduct value and how the standard uses it.

Where a deduct value comes from

The inspector records the type, severity and quantity of each distress in a sample unit. The standard then gives these steps (ASTM D5340, 9.1 to 9.3):

  1. Add up the quantity of each distress type at each severity level. The unit is area, length or number of occurrences, depending on the type.
  2. Divide each quantity by the area of the sample unit and multiply by 100. This is the percent density.
  3. Read the deduct value on the deduct curve for that distress type and severity.

For concrete, the density is the percent of slabs in the sample unit that have the distress (10.1 and 10.2).

The deduct curves

Each distress type has its own curves. The asphalt curves are in Appendix X3, and the concrete curves are in Appendix X4. A curve plots the deduct value from 0 to 100 against the distress density in percent, on a logarithmic scale from 0.1 to 100. The curves for alligator cracking, block cracking and corrugation (Figures X3.1, X3.3 and X3.4) have one line for each severity level: low, medium and high. The bleeding curve (Figure X3.2) has one line.

On those four curves, a higher density gives a higher deduct value. At the same density, a higher severity gives a higher deduct value.

From deduct values to the PCI

The standard first checks how many deduct values are greater than 5.

  • None or one above 5. Use the total deduct value as the maximum CDV.
  • Two or more above 5. Find the maximum CDV with the iterative procedure below.

The iterative procedure (9.5 and 10.3) works like this:

  1. Find HDV, the highest deduct value, and calculate m = 1 + (9 / 95) x (100 - HDV). The value of m is at most 10.
  2. Keep the m largest deduct values. Multiply the last one by the fractional part of m.
  3. Sum the deduct values, and count q, the number of values greater than 5.
  4. Read the CDV from the correction curve for q and the sum.
  5. Reduce the smallest deduct value that is greater than 5 to 5. Repeat steps 3 to 5 until q is 1.
  6. The maximum CDV is the largest CDV from all the passes.

Then PCI = 100 - maximum CDV. The correction curves are Figure X3.19 for asphalt and Figure X4.16 for concrete.

A worked example for jointed concrete

The PCI page works an asphalt example. This one uses the concrete sample unit of ASTM D5340 Figures 7 and 8.

The highest deduct value is 32.0, so m = 1 + (9 / 95) x (100 - 32.0) = 7.44. The standard keeps the seven largest values and 0.44 of the eighth. The sheet lists 32.0, 12.0, 11.0, 10.0, 9.0, 8.0 and 6.0, and 1.3 for the last. The passes give these results:

PassChangeSumqCDV
1none, all seven values above 589.3756.0
26.0 becomes 5.088.3658.0
38.0 becomes 5.085.3558.0
49.0 becomes 5.081.3458.0
510.0 becomes 5.076.3357.0
611.0 becomes 5.070.3261.0
712.0 becomes 5.063.3163.3

The sum falls by the amount of each reduction, for example 89.3 - 1.0 = 88.3. The CDV does not fall with it. It drops to 57.0 at q = 3 and then rises to 63.3. The largest value is the maximum CDV, so the PCI of the sample unit is 100 - 63.3 = 36.7.

Deduct value, CDV and PCI

  • Deduct value. One number for one distress type and severity at its density.
  • Total deduct value. The sum of the deduct values that the procedure keeps.
  • Corrected deduct value. The value that the correction curve gives for a total and a q.
  • Maximum CDV. The largest CDV of all the passes. The PCI is 100 minus this value.

What a deduct value does not show

A deduct value comes from distress that the inspector sees on the surface. It does not come from a measurement of structure. This page follows the 1998 edition of ASTM D5340. The current edition is D5340-24, and its text was not read. Use the edition that the survey contract names.

Drones

A drone can capture the images from which an inspector records distress. TarmacView’s pavement condition assessment captures the pavement photos. Crack detection and the ASTM D5340 rating are in development, and it does not compute a PCI yet. The service is offered as early access.

Frequently Asked Questions

What is a deduct value in the PCI?
A deduct value is the number that an ASTM D5340 deduct curve gives for one distress type at one severity and density. The inspector reads one deduct value for each distress and severity combination in a sample unit. The deduct values lead to the PCI, and the PCI is 100 minus the maximum corrected deduct value.
How do you find a deduct value?
Divide the quantity of the distress by the area of the sample unit and multiply by 100 to get the percent density. Then read the deduct value on the deduct curve for that distress type and severity. ASTM D5340 gives the asphalt curves in Appendix X3 and the concrete curves in Appendix X4.
What is the corrected deduct value (CDV)?
The corrected deduct value is a value that ASTM D5340 reads from a correction curve. The inputs are the total of the deduct values and q, the number of deduct values above 5. The standard repeats the step, and the largest CDV is the maximum CDV. The PCI is 100 minus that maximum.
Why does the PCI procedure reduce deduct values to 5?
The standard reduces the smallest deduct value above 5 to 5 and reads the CDV again, until q is 1. Each pass lowers q by one. A deduct value of 5 or less does not count in q. The largest CDV of all the passes is the maximum CDV.
How many deduct values does the PCI use?
At most m values, with m = 1 + (9 / 95) x (100 - HDV). HDV is the highest deduct value, and m is never more than 10. If m is 7.44, the seven largest values count in full. The eighth counts by its fractional part.
When do you not need the iterative procedure?
If none or only one deduct value is greater than 5, ASTM D5340 uses the total deduct value as the maximum CDV. The PCI is then 100 minus that total. The correction curves apply only when two or more deduct values are above 5.
Is the deduct value the same for asphalt and concrete?
No. ASTM D5340 gives separate deduct curves for asphalt and for jointed concrete, with their own correction curves. The correction procedure is the same for both. For concrete, the density is the percent of slabs that have the distress.

References

astm-d5340-98
ASTM D5340-98, Standard Test Method for Airport Pavement Condition Index Surveys ASTM International

This is a reference entry. TarmacView provides drone inspection services and doesn't sell the equipment or materials described in this glossary.

Get Started Need your airfield lighting verified? TarmacView inspects PAPI, runway and approach lighting by drone, between aircraft movements, and delivers a compliance report built for your regulator. Pavement and obstacle inspection are in development.
Keep reading

Learn more

06 PAGES

Related terms

03 TERMS
Pavement Condition Index (PCI): ASTM D5340 and D6433
glossary

Pavement Condition Index (PCI): ASTM D5340 and D6433

The Pavement Condition Index (PCI) is a rating from 0 to 100 for the surface condition of a pavement. The formula and a worked example, the rating scale, how a survey works, ASTM D5340 and D6433, and what the PCI does not measure.

ASTM D5340
glossary

ASTM D5340

ASTM D5340 is the test method for airport Pavement Condition Index (PCI) surveys. The edition code, the rating scale, sampling, how the PCI is calculated, and what the PCI does not measure.

Pavement Distress Survey
glossary

Pavement Distress Survey

A pavement distress survey records the type, severity and quantity of every distress on a pavement. Which manual to use, how sampling works, how distresses combine into a PCI, and where drones fit.

Further reading

03 ARTICLES
Pavement Condition Index Explained
Pavement Condition Index Explained
blog

Pavement Condition Index Explained

What PCI is, how ASTM D5340 turns observed distress into a 0-100 number, what the deduct-value step does, and what the index cannot tell you about a…

AUG 15 2026 9 MIN
Pavement Design Life and When an Overlay Is Due
Pavement Design Life and When an Overlay Is Due
blog

Pavement Design Life and When an Overlay Is Due

Why a single survey cannot drive an overlay decision, and why a trend across years tells you the deterioration rate that actually matters.

AUG 28 2026 9 MIN